500,000 gal. Water Tank
Project pictures



01.jpg
01.jpg
640x480x16M
[50 KB]
 The beginning of the construction of the tank with the excavation of the footings. 02.jpg
02.jpg
640x480x16M
[50 KB]
 The construction of the footings continues with the formwork.
03.jpg
03.jpg
640x480x16M
[51 KB]
 The footings are poured and the pedestals are formed. 04.jpg
04.jpg
640x480x16M
[51 KB]
 Some of the risers have been poured while others are still in the process of having the steel and formwork added.
05.jpg
05.jpg
640x480x16M
[52 KB]
 All of the risers have been poured and the backfilling of the foundations is about to commence. 06.jpg
06.jpg
640x480x16M
[53 KB]
 A view of the foundations from ground level.
07.jpg
07.jpg
640x480x16M
[50 KB]
 Another view of the foundations during construction from inside the excavation. Image01.jpg
Image01.jpg
640x480x16M
[48 KB]
 Setting up the construction crane.
Image02.jpg
Image02.jpg
640x480x16M
[49 KB]
 A lot of equipment is needed for the construction of a water tank. Image06.jpg
Image06.jpg
480x640x16M
[19 KB]
 The erection of the first leg of the tank.
Image08.jpg
Image08.jpg
640x480x16M
[53 KB]
 More sections of the crane with a view to the North of the site (Temple Baptist Church in the background). Image12.jpg
Image12.jpg
640x480x16M
[44 KB]
 A view of the bottom of the tank riser during construction.
Image13.jpg
Image13.jpg
640x480x16M
[50 KB]
 Another view of the bottom of the tank riser during construction. Image14.jpg
Image14.jpg
640x480x16M
[49 KB]
 Welders setting up.
Image15.jpg
Image15.jpg
640x480x16M
[24 KB]
 Work on the riser pipe continues. Image18.jpg
Image18.jpg
640x480x16M
[25 KB]
 And continues some more.
Image21.jpg
Image21.jpg
640x480x16M
[48 KB]
 Sections of the tank legs are hoisted by the crane. Image22.jpg
Image22.jpg
640x480x16M
[49 KB]
 The sections are then welded in place by the contractors personnel.
Image25.jpg
Image25.jpg
640x480x16M
[45 KB]
 The legs are finally all in place. Image26.jpg
Image26.jpg
640x480x16M
[50 KB]
 The first sections of the elevated tank itself are raised by the crane.
Image27.jpg
Image27.jpg
640x480x16M
[46 KB]
 The sections are hoisted carefully and placed at their final location. Image28.jpg
Image28.jpg
640x480x16M
[45 KB]
 . . . placement of the tank sections.
Image29.jpg
Image29.jpg
640x480x16M
[36 KB]
 The first section is finally in place. Image30.jpg
Image30.jpg
640x480x16M
[46 KB]
 The second section is on its way.
Image31.jpg
Image31.jpg
640x480x16M
[54 KB]
 The second section is placed. Image34.jpg
Image34.jpg
640x480x16M
[46 KB]
 And they're finally placing the last sections of the tank. It looks complete except for the painting.
Image35.jpg
Image35.jpg
640x480x16M
[51 KB]
 The tank is complete and the view to the East is pretty good. Image36.jpg
Image36.jpg
640x480x16M
[44 KB]
 The view north along Oak Grove Road is pretty good too!
Image41.jpg
Image41.jpg
640x480x16M
[51 KB]
 But the view down is pretty scary (glad I didn't have to climb that thing). Image43.jpg
Image43.jpg
640x480x16M
[37 KB]
 Here's a good view of the new Oak Grove School from the top of the tank. Don't you kids get any ideas!
Image46.jpg
Image46.jpg
640x480x16M
[38 KB]
 The tank from the ground underneath.    